Summary of Proposed Depot Alterations and Removals


FIRST SUB-DIVISION

White Pine Depot
Frame, 18 by 24 feet
Remove and salvage
0090 Salvage
0275 OE
0000 A and B
0185 Net RFA
0275 Total estimated expenses

Hope Depot
Frame, 22 feet six inches by 103 feet four inches
Remove 72 feet at east end, convert present waiting room into freight room, sub-divide present ticket office into waiting room and ticket office, and replace plank platform with Marshall fines
Sketch by Division Engineer, Spokane, April 17, 1944
0175 Salvage
1045 OE
0625 A and B
1500 Net RFA
1670 Total estimated expenses

Kootenai Depot
Frame, 30 by 82 feet
Remove depot and platform and build small shed for housing mail
Sketch by Division Engineer, Spokane May 11, 1944
0175 Salvage
0440 OE
0150 A and B
0415 Net RFA
0590 Total estimated expenses

Sandpoint Watchman's Shack
Frame, remove
0050 Salvage
0060 OE
0000 A and B
00(10) Net RFA
0050 Total estimated expenses

Otis Orchards Depot
Frame, 30 by 32 feet
Remove depot and construct shed for use of mail and telephone
Sketch by Division Engineer, Spokane, May 11, 1944
0100 Salvage
0220 OE
0150 A and B
0270 Net RFA
0370 Total estimated expenses


SECOND SUB-DIVISION

Tyler Depot
Frame, 24 by 55 feet
Remove depot and construct shed 10 by 16 feet from salvaged material
0090 Salvage
0330 OE
0160 A and B
0400 Net RFA
0490 Total estimated expenses


THIRD SUB-DIVISION

Kiona Depot
Frame, 15 feet by 74 feet eight inches
Remove 43 feet eight inches at east end and close up sliding door opening
Sketch by Assistant Engineer, Pasco, June 5, 1944
0050 Salvage
0315 OE
0245 A and B
0510 Net RFA
0560 Total estimated expenses

Mabton Depot
Frame, 22 feet six inches by 128 feet one inch
Remove 45 feet from east end including platform, raise building 12 inches, renew foundation, make interior alterations and place two new concrete septic tanks
Sketch by Division Engineer, Spokane, May 23, 1944
0055 Salvage
2305 OE
1250 A and B
3500 Net RFA
3555 Total estimated expenses


FOURTH SUB-DIVISION

Grandview Depot
Frame, 24 by 79 feet
Remove 32 feet from east end, remove 28 feet from west end, make interior alterations on balance of depot for purposes
Sketch by Division Engineer, Spokane, May 10, 1944
0050 Salvage
0935 OE
0610 A and B
1495 Net RFA
1545 Total estimated expenses

Sunnyside Depot
Frame, 24 by 93 feet
Remove 50 feet from east end, make alterations on balance, re-shingle and paint
Sketch by Division Engineer, Spokane, May 10, 1944
0060 Salvage
0945 OE
0325 A and B
1210 Net RFA
1270 Total estimated expenses


NINTH SUB-DIVISION

Burbank Depot
Frame, 24 by 36 feet
Remove present depot and place shelter shed recovered from P and L Branch
0090 Salvage
0330 OE
0160 A and B
0400 Net RFA
0490 Total estimated expenses


TOTALS
0990 Salvage
7190 OE
3675 A and B
9875 Net RFA

$10,865 Total estimated expenses

Office of Assistant Chief Engineer
Seattle, Wash., June 14, 1944


SOURCE:
File 9774, Chief Engineer's Subject Files, Northern Pacific Collection, Minnesota Historical Society, Box 134.K.3.10F



Author: John A. Phillips, III. Title: Idaho Division Depot Doings. URL: www.employees.org/~davison/nprha/idahodepots.html.